TPO – After more than 1 year of construction, the Quang Ngai – Hoai Nhon expressway project has gradually taken shape, some construction items have been completed ahead of schedule, 2/3 of the mountain tunnel has been completed. dug through… The output reached about 22% of the total volume.

Speeding

The project to build the Eastern North – South Expressway, period 2021 – 2025, the Quang Ngai – Hoai Nhon section has a length of 88km, passing through the territory of Quang Ngai province (60.3km) and Binh Dinh province ( 27.7km), total investment is more than 20,000 billion VND, of which construction value is nearly 14,500 billion VND.

Regarding site clearance work, up to now it has reached 96%, of which Binh Dinh province handed over 100%, Quang Ngai province handed over 95%. In addition, 16/19 mines have been licensed, and the remaining 3 mines will be licensed in April 2024.

What is the status of the Quang Ngai - Hoai Nhon Expressway project after more than 1 year of construction?  photo 2
The road surface on the Quang Ngai – Hoai Nhon highway gradually shows its shape.

On the route, there are 3 tunnels through the mountain (tunnel 1 is 610m long, tunnel 2 is 698m long, tunnel 3 is 3,200 km long), along with 77 bridges, 586 culverts, 81 underground tunnels, the largest of which is the bridge across the Ve River connecting the two. Mo Duc and Tu Nghia districts (610m long, longest bridge on the route). Currently, tunnels No. 1 and No. 2 have been dug many months ahead of schedule. In addition, 58/77 bridges were constructed and 3.3/12.1 million m3 of road embankment was built. The realized output reaches about 22% of the total volume.

Mr. Nguyen Quang Huy – Deputy General Director of Deo Ca Group said that after digging, tunnels No. 1 and No. 2 will be used as public service roads, shortening transportation time and coordinating materials throughout the route. , helping to speed up the construction progress of the entire project.

Tunnel No. 3 in particular is the longest mountain-crossing tunnel on the North-South expressway, connecting the two provinces of Quang Ngai – Binh Dinh. Due to complex geology, the construction work was carried out very carefully by the contractor to ensure quality, safety. To date, the left tunnel has reached 796/3,200m, the right tunnel has reached nearly 854/3,200m.

What is the status of the Quang Ngai - Hoai Nhon Expressway project after more than 1 year of construction?  photo 3

Ve River Bridge connecting Mo Duc and Tu Nghia districts (Quang Ngai) is the largest bridge on the Quang Ngai – Hoai Nhon highway with a length of 610m.

“According to the contract signed with the investor, tunnel No. 3 will be completed after 42 months of construction, but the group is making efforts to clear this special-level road tunnel earlier than planned. It is expected that tunnel 3 will be dug through. in June 2025″, Mr. Huy added.

Currently, all 3 packages (XL1, XL2, XL3) of Quang Ngai – Hoai Nhon Expressway are organized in 3 shifts with 43 construction jobs, with more than 3,200 personnel, and 1,100 equipment and machinery on the construction site. As for the tunnel items, the contractor carries out construction continuously 24/24, with engineers and workers taking shifts to work continuously without stopping.

What is the status of the Quang Ngai - Hoai Nhon Expressway project after more than 1 year of construction?  photo 4What is the status of the Quang Ngai - Hoai Nhon Expressway project after more than 1 year of construction?  photo 5What is the status of the Quang Ngai - Hoai Nhon Expressway project after more than 1 year of construction?  photo 6

Nearly 3,200 employees and more than 1,100 machines and equipment work in shifts continuously on the construction site.

According to Mr. Nguyen Quang Huy, the plan proposed in 2024 strives to achieve a cumulative output of about 7,500 billion VND. Particularly for tunnels No. 1 and No. 2, the road surface, tunnel lining and equipment will be completed. In addition, 60/77 bridges have been constructed (priority is given to completing cross-road overpasses), completing road base embankment and partially constructing asphalt concrete for traffic safety.

Land clearance problems and material quarries

As noted by the reporter, at the beginning of route Km0+800 of package XL1 (through Nghia Ky commune, Tu Nghia district). This location is designed to build an overpass connecting the Quang Ngai – Hoai Nhon expressway with the Da Nang – Quang Ngai expressway, but the construction units have not yet fully handed over the site. On the route, there are still 50 households that have not agreed to receive compensation, and 99 houses have not been dismantled or relocated.

What is the status of the Quang Ngai - Hoai Nhon Expressway project after more than 1 year of construction?  photo 7What is the status of the Quang Ngai - Hoai Nhon Expressway project after more than 1 year of construction?  photo 8

Construction workers digging tunnel No. 3.

Leaders of Deo Ca Group said that on the Quang Ngai – Hoai Nhon expressway, there are currently about 20 locations that have not been cleared. In particular, critical progress locations such as the intersection at the beginning of the route (Tu Nghia district), National Highway 24 overpass, Eo Gio bridge, Song Quan bridge (Duc Pho town) and technical infrastructure works on the route are slow to move. move.

For material mines, in Quang Ngai province, the licensed reserves are 5.3 m3 of soil and 0.24 million m3 of sand. However, the compensation costs of some mines are higher than the regulations (about 3 times), there is no access road, leading to the actual mine reserves being exploited only reaching 3.2/5.3 million. m3 of soil and 0.1/0.24 million m3 of sand.

What is the status of the Quang Ngai - Hoai Nhon Expressway project after more than 1 year of construction?  photo 9

At the beginning of route Km0+800 of package XL1 (through Nghia Ky commune, Tu Nghia district), many houses are entangled.

According to Deputy General Director of Ca Pass Group Nguyen Quang Huy, currently both XL1 and XL2 bidding packages in Quang Ngai province are having problems with site clearance and material quarrying. Therefore, the progress of implementing the Quang Ngai – Hoai Nhon expressway project in this year’s dry season has not achieved high results. Currently, 16/19 material mines have been licensed for highways. The number of mine licenses is relatively large but in reality only a small quantity can be exploited due to difficulties in access and transportation.

“The Group hopes that Quang Ngai province will coordinate with the investor to soon remove problems related to site clearance and material mines, to comply with the commitment to complete site clearance work on the entire route, and hand over to the contractor. before April 30,” Mr. Huy shared.

What is the status of the Quang Ngai - Hoai Nhon Expressway project after more than 1 year of construction?  photo 10What is the status of the Quang Ngai - Hoai Nhon Expressway project after more than 1 year of construction?  photo 11

Tunnel No. 3 is the longest mountain tunnel on the North-South expressway. To date, the left tunnel has reached 796/3,200m, the right tunnel has reached nearly 854/3,200m.

Mr. Tran Phuoc Hien – Vice Chairman of Quang Ngai Provincial People’s Committee said that completing the handover of the Quang Ngai – Hoai Nhon Expressway (section passing through Quang Ngai province) before April 30, 2024, is determined to be a milestone. is one of Quang Ngai’s top tasks to bring this key project to an early finish line.

In the process of resolving compensation problems, it is necessary to ensure the highest benefits for people according to the provisions of law. If it’s not legitimate, don’t make any promises or give a clear answer so people don’t misunderstand and voluntarily hand over the premises.

What is the status of the Quang Ngai - Hoai Nhon Expressway project after more than 1 year of construction?  photo 12What is the status of the Quang Ngai - Hoai Nhon Expressway project after more than 1 year of construction?  photo 13

The tunnel item is constructed continuously by the contractor 24/24, with engineers and workers taking shifts to work continuously without stopping.

In cases where the site is cleared and handed over, the remaining area within the expressway safety corridor will be compiled and sent to the Provincial People’s Committee to propose to the Ministry of Transport to consider a resolution mechanism.

Quang Ngai – Hoai Nhon Expressway Project (belongs to the eastern North-South Expressway construction project in the period 2021-2025). This is the largest scale project among the 12 component projects of the North-South Expressway Project.

The project has a length of 88km, total investment of more than 20,400 billion VND. The section through Quang Ngai province is 60.3km long, and the section through Binh Dinh province is 27.7km long. Phase 1, Quang Ngai – Hoai Nhon expressway has 4 lanes, speed of 80km/h. The project is invested by Project Management Board 2 (Ministry of Transport).

According to the plan, the project must complete the entire route in the third quarter of 2026.

Quang Ngai plans to enforce and hand over 100% of the expressway site before April 30
Quang Ngai plans to enforce and hand over 100% of the expressway site before April 30

Why did the locality ask to delay the handover time of the Quang Ngai - Hoai Nhon expressway?
Why did the locality ask to delay the handover time of the Quang Ngai – Hoai Nhon expressway?

Open 2 tunnels on Quang Ngai - Hoai Nhon highway
Open 2 tunnels on Quang Ngai – Hoai Nhon highway

Nguyen Ngoc

[ad_2]

Original Source Link

نيك مربرب esarabe.com افلام سكس لمايا خليفه maiden in black hentai justhentaiporn.com saijaku no bahamut hentai manga xxx sexy hd xbeegporn.mobi filmyzilla punjabi footjob indian 2beeg.net gujarati sexy open video بزاز دوللي شاهين timerak.com اغتصاب بالقوة سكس وايف 3gpjizz.info تشارلز ديرا bengali porn picture redwap.xyz mobi22 kanada sex vedio xshaker.net village sex new outdoor sex xvideos pakistanisexporn.com south hero hindiblufilm tryporno.net sexindia new3gpmovies russianporntrends.com xx video gujarat pondy gay sex dampxxx.org epornor www indiansix freepakistaniporn.com englishsexvedio ايطالي سكس pornvuku.net نيك قوي جدا سكس اجمل امراه meyzo.mobi قصص اغتصاب جنسية